Entessar-5.jpg

Modification and pigging of 20” Entessar-Sarir pipeline at 114 Km.

Cleaning the 20” pipeline by using bi-direction pigging by nitrogen gas.
Purging the 20” pipeline by nitrogen gas before stating cutting the line.
Constructed temporary condensate pit as per specification.
Install temporary flare for burning the gas during pigging activity.
Using special insulation during welding activity.

    Project Details

    Category :

    pipes

    Client :

    General Company for Gas Transmission and Distribution

    Date :

    August 11, 2020